1775 Old 6 Road
PO Box 535
Brooklyn, IA 52211
Phone: 641-522-9206
fax: 641-522-5594

Menu
 
Company 
Services   
Employment 

 

 

 


   

 

 

 


 

 

   


 

The 2002 construction season is winding down as Thanksgiving day approaches. Other than the two week period of rain in the last part of October, our fall season has been pretty good for pushing the completion of projects. With the late spring starts in several divisions, the good fall weather has provided for some opportunity to fill up the season.

As of November 22nd, both crews are up in Grundy County working on the new Highway 20 paving projects. Virg and his crew have been laying shoulder stone and doing some subdrain work on the Manatt portion of this construction project. Bob and his crew are finishing up on Carlson's east portion of Highway 20. This project will then tie into Irving Jensen's 6 mile stretch of new pavement. They will have installed over 71,000 feet on Carlson's section and will have approximately 74,000 feet available to install on Jensen's. This project does not have to be completed this year. Once the weather starts closing in, they will shut down for the year. As of today, this will bring the approximate total installed to 660,000 feet.

At the start of the year I wasn't expecting to even have 500,000 feet the way the lettings were going! This crew also laid several thousand tons of shoulder stone to fill in between subdrain projects. We have approximately 200,000 feet on the books for next year and will be hitting every letting hard to fill another season.

Sealcoating finished a strong season by combining several stabilization projects. It was a season mainly comprised of city, county and a very small portion of state work.

One state project that we were awarded in the August letting launched Manatt's down another avenue in providing recycling and stabilization options. The project was 20 lane miles of full depth shoulder recycling and stabilization using foamed asphalt. This process has been used in several western states and is slowly working its way east. This was a test project for the Iowa DOT and they were very impressed with the results.

Foamed asphalt is a controlled process in which hot asphalt cement (350 degrees) comes in contact with a small amount of water. The asphalt cement explodes into millions of bubbles. In this form the volume of asphalt expands as much as 15 times, drastically reducing viscosity. While in this state, the asphalt is mixed with a cold moist aggregate. The bubbles formed burst when they come into contact with the aggregate, uniformly dispersing amongst the fine particles to form a stable mortar. The reaction time lasts for only 10 to 20 seconds for mixing as the asphalt returns to its normal liquid state. This process allows for the use of smaller amounts of asphalt cement per square yard because it has far better particle coverage.

The Wirtgen WR2500, that we have just recently purchased, is equipped with the foamed asphalt system. It has a thermostatically controlled heating system for the asphalt lines and spray bar. The spray bar is made up of 16 expansion chambers where the asphalt cement is introduced to the water and air mixture. This spray bar directs the foamed asphalt into the cutting head chamber and is then mixed with the recycled (pulverized) material. The recycler machine is coupled to, and pushes an asphalt tanker, plus, pulls a truck with a water tank. (See pictures above.) Compaction is done directly behind the machine starting with a 12 ton vibratory pad foot roller (see picture #2 below). Blading of material is done as the material is moist and then rolled again with a rubber tire roller (see picture #3 below). The final surface is rolled with a smooth drum roller (see picture #4 below).


Picture #2:
Vibratory Pad, Foot Roller,
& Motor Grader


Picture #3:
Rubber Tire Roller


Picture #4:
Smooth Drum Roller

The original contract was bid with one mix design for construction. As test results came back, it became evident that some changes were going to have to be made to achieve finished minimum construction densities. The biggest change was the addition of Portland cement to the design, which was later changed to fly-ash. Other mix design changes involved different percentages of asphalt cement being added for foaming in addition to crushed shoulder stone for added stability.

This project was a learning experience for all involved. For our first week of operation we had the knowledge and help from some international engineers to educate ourselves with the process. Marcus Stockhausen from Windhagen, Germany with the Wirtgen group worked directly with Kurt in the operation of the foamed asphalt system on the machine. Eric Uppink from Kloof, South Africa who is a civil engineer technician with Louden International worked with Virg, Jeremy and myself in the construction process of this project. Their expertise was greatly appreciated!

This project is going to open the door for several more opportunities to utilize this process at the State and County levels!

I want to thank Kurt, Virg, Jeremy and the whole sealcoat crew for the professional attitude and quality-minded completion of this project. Everyone and every piece of equipment had a direct effect on the outcome of the final product. Several times, on the go, ingenuity was used which shows what this crew can really do when put to the challenge.

I also would like to thank Mark Olson and Dave Sanders for putting up with the added challenges of spreading the fly-ash and cement. Carmen and the weld shop went the extra mile to fit us in for our equipment modifications, hats off to them!

Brett Strong dropped in for a couple of days showing his versatility! Also, Phil Maddison and his milling crew along with thanks to the Ames Division for the water truck and trucking needs. I'm sure I missed someone, but it was not intentional!

My last "att-a-boys" go out to Bob and the subdrain crew. The last few years the competition has been tough and the volume of work has declined. We managed another respectable year and that is due to your superior work ethic and determination.

The projects have changed and involve a lot more, stop and go construction, plus a higher level of labor. I try my best to schedule projects in a logical order, but when you are the sub-contractor, you go as the prime contractor fills his schedule.

I don't get out to the jobs like I used to as 3 divisions are a true handful when running a full schedule, but I still realize the added efforts you put in for these "not so easy projects." Bob's crew, along with the group of trucks that follow him around, make this crew the best subdrain crew in the state! Thanks for the extra efforts you put in as well as your safe driving.

With this, I close wishing you all a Happy Holidays and Happy New Year! Take time to enjoy your families and time off! Continue to practice safe habits even at home and I look forward to a safe and productive 2003 season!