Highway 63

Asphalt

Highway 63 overlays

Manatt's Newton Asphalt and Milling Division completed four different spot overlays at 2" and 3" in depth over the 8 mile long project. It took 10 total datys to complete 12,900 tons of HMA (Hot Mix Asphalt)

TAKEAWAY

The team stayed the course through multiple weather challenges

projects

See more of what we’ve built.

https://www.high-endrolex.com/11